Fleximmer. The dimmer for data centre power.

Why now

Grid capacity now sets the pace for data centres.

Data centres need more electricity. In many markets, the grid cannot connect them on firm terms when they need it. Regulators and grid operators are writing new connection rules in response, and several of those rules now ask data centres for flexibility, controllability or on-site resources.

01 · Demand

Demand is rising.

Great Britain

~73GW

of contracted data-centre demand in the connection queue by June 2025, from about 315 projects. Britain’s peak demand in 2025 was 45 GW.1

Europe

9.2 →26.6GW

Installed data-centre capacity could reach 26.6 GW by 2035, up from around 9.2 GW in 2025.2

Global

88 →340GW

Installed data-centre capacity could reach up to 340 GW by 2035, up from 88 GW in 2025.3

02 · Connections

Connections cannot keep up.

Europe’s main hubs

7–10years

A data centre typically takes one to two years to build. In Frankfurt, London, Amsterdam, Paris and Dublin, the wait for a grid connection averages seven to ten years.4

Denmark

~60GW

In March 2026, Denmark’s transmission operator paused new connection agreements for three months. Around 60 GW of new demand was waiting to connect, against a national peak of about 7 GW.5

03 · The cost of waiting

Waiting is expensive. So is flexibility done badly.

A data centre that cannot connect cannot earn. But flexibility only pays when it protects the commitments a data centre has made to its own customers.

The value of connecting sooner

up to$8mper MW

BCG modelled an AI data centre in north-west Europe and put the value of connecting up to three years sooner on non-firm terms at up to $8 million per MW of capacity.6

The cost of unmet demand

1.5–2%of profit, per 1% unserved

The same study estimates that each 1% of compute demand a data centre cannot serve costs about 1.5–2% of its profit.6

Figures from third-party models of reference sites. They describe the sector, not Fleximmer results.

04 · Rules by market

Flexibility is becoming part of the connection.

In the markets below, governments, regulators and network operators now ask data centres for flexibility, controllability or on-site resources, or offer connections on those terms. Each country writes its own rules.

  • United Kingdom

    The government’s Data Centre Covenant sets out expectations for data centres. It says they “should also support grid resilience, flexibility and clean power”, and expects “credible commitments for the grid capacity they request”.7

    Asks
  • Finland

    Under Fingrid’s grid code specifications of June 2026, new demand sites of 30 MW and above that connect directly to the transmission grid, including data centres, are to be able to reduce their power by at least 30% on request.8

    Asks
  • Spain

    Since 1 September 2026, demand can connect under flexible access permits. Grid operators can limit flexible consumption in exchange for access.9

    Offers
  • Netherlands

    Time-bound transport rights give transport for at least 85% of the hours in a year.10

    Offers
  • Germany

    The Energy Industry Act lets network operators offer a flexible grid connection agreement. It is an option for the operator, not a duty.11

    Offers
  • United States

    FERC has accepted, subject to conditions, a non-firm service in the SPP region. Under it, large loads can take power on an as-available basis while network upgrades for firm service are built.12

    Offers
  • Ireland

    New data centres must bring on-site or nearby generation or storage capacity.13

    Asks
Offers flexible or non-firm connections Asks large new loads for flexibility or their own power

Research points the same wayA Duke University study estimates that the US grid could integrate 76 GW of new load if that load accepted curtailment for 0.25% of its maximum uptime, with curtailment events averaging under two hours.14

05 · What this asks of a data centre

Every route asks one question: how much can this site safely give back?

It is not the sum of the nameplate ratings. IT workload, batteries and cooling draw on the same limits.

It is not one number. It changes with the hour, how long the grid needs it, how often it calls, and how fast the site recovers.

It cannot cost a customer. SLAs and backup reserves come first.